The Amador County Planning
Commission was packed this week for the consideration of the expansion of the
Jackson Valley Quarry by George Reed, Inc. This would expand the mining operations of the Jackson
Valley Rd property currently mined for rock by George Reed, Inc. The
proposal is to expand the 74 acre quarry with 500,000 tons per year of product
to the adjoining parcel of approximately 85 acres. The county’s Technical
Advisory Committee previously
reviewed this request and suggested that the two parcels in question may need
to merged because of the pit location. Also, of concern was a traffic
study in regards to increased hauling by trucks traveling to and forth from the
facility, as well as a mitigation plan for the traffic.
George Reed Inc did not respond to
requests for a traffic study initially so the county again requested these
documents to which George Reed responded on Dec 5th with some
additional documentation. George Reed Inc representative Don Dane,
scientific engineering consultant who complies with California Environmental Quality
Act documentation for the rock mining company, approached the commission and
spoke about the preparation of the mitigation efforts for the traffic impacts.
Dane stated that he was waiting until he heard more public comment before
preparing any environmental mitigation plans as an explanation as to why there
had been no plans presented by the applicant George Reed, Inc. George Lambert, a Jackson Valley Resident told
the commission that his concerns include that in no way can any environmental
reports show the impacts of removing an entire hill and replacing it with a
huge hole brimmed with trees.
The current quarry is what it is, it is,
and looks like, a quarry stated Lambert. There is noise pollution associated
with the sounds of crushing and conveyer belts echoing through the valley.
Lambert also expressed concerns that a large gap has been opened between his
property and Hwy 88 because of the removal of the hillside across from the
Greenstone Winery. This has now created traffic noise at his home that was
previously not heard. The amount of traffic Lambert states, by the applicants own admission, will
increase dramatically. Also, he said, to be considered is the Buena Vista
casino impacts as a cumulative effect on the Jackson Valley area.
Traffic was a main concern of all residents of the area, as was the performance
of a full environmental impact report requirement by the Planning Commission
for the consideration of the approval of the project. New resident Bill May,
stating that his new home will ready to move into around Easter of 2007, cited concerns about the
disposition of wildlife on the property. “Its not quarry property- its horse
country” states May.
May cites the Amador County Transportation
Commission’s response to notification of the project with concerns of roadway
condition mitigations. May cites the original use permit for the existing
quarry which requires that George Reed maintain the roadway between the current
quarry and Hwy 88. May states that if that is an example of how they will
maintain the new portions of the road impacted by their haulers- it is
unacceptable. Many other residents of the general area also approached the
Commission stating that although they did not live close enough to receive
notification of the planning commission’s hearing they still have concerns
about what was characterized as the constant assault the Jackson Valley region,
one of the prime agricultural areas of the county. Quarries, the Co-generation Plant, the fireworks
plant and low income housing were all cited as assaults on the valley.
Weight limits on the roadways were also discussed as was the noise, vibrations,
dust and damage to local homes from blasting at the quarry.
The trainer of the Lost
Trails Ranch located on Martin Lane spoke about the amount of dust that comes
the way of the ranch after blasting as well the impacts of the sounds and
vibrations to the valuable show horses at the ranch. The Planning Commission discussed the visual
aesthetics and established after much discussion that the impacts are
significant, as are the potential impacts to agriculture in the area,
specifically the blasting impacts on air, horse production and training.
Also, cultural and geological impacts were cited as concerns. Geological
concerns and the lands ability to support a septic system were ruled less than
significant impacts however ultimately the Planning Commission will require a
full environmental impact report to be completed by George Reed, Inc, at least
for the items considered significant impacts. After the draft is completed a public
hearing will once again be held.
|