Representatives of Jackson, Sutter Creek, Ione, ARSA, the AWA,
as well as HDR all joined together yesterday to discuss short term improvements
to meet the needs of local wastewater demands. In the audience
representatives of the Foothill Conservancy, Present in the audience were Nolte
Engineering of the Jackson
Hills project, Castle
Oaks Golf course, JTS Communities, and the Gold Rush and Wicklow Way subdivisions. County Administrative
Officer Patrick Blacklock facilitated
the meeting while representatives from HDR Engineering Inc. summarized the
results of the last few meetings and went over some of the steps that can be
taken in the future to ensure capacity for the development that is already on
the books.
Rob Williams of HDR reiterated
that at the meeting held October 25th 3 Regional Treatment
Alternatives emerged. Those included a Regional Plant in the Martell Area, a Regional Plant
in the Sutter Creek area or Sub-Regional Plants in both Martell and Sutter
Creek. He then presented the conclusions from the December 4th
meeting. It was determined at that meeting that present worth costs are similar
for all the treatment options mentioned above.
Also, discussed was that projected wastewater flows will
exceed the Sutter Creek Plant’s capacity within a few years, even with
expansion. However it was determined that the expansion of the plant is
key to wastewater issue resolution in the short term as the expansion of the
plant can be achieved more quickly and be on line nearly a full two years before
a new Regional Plant. The life expectancy of the existing Sutter Creek Plant is
probably less than 10 years, if even that said, Rob Williams. A Technical
Memorandum has also been developed outlining the capacity of the existing
Sutter Creek Plant. Williams then proceeded to go over the approximate current flows to the Sutter
Creek plant which totaled 327,000 gallons per day. According to data gathered
274,200 of those gallons are from Sutter Creek, 22,000 from Amador City
and the remaining 53,800 from the Martell Area.
The Sutter Creek Plant
is permitted for 480,000 gallons per day but preliminary data indicates that
the city may not be able to meet state required testing levels even 80,000
gallons below that capacity at 400,000 gallons. ARSA and Sutter Creek City
Manager Rob Duke explained that based upon HDR’s research the plant may not be able
to meet testing standards above 400,000 gallons a day. According to HDR the estimated short-term
capacity is 172,000 gallons per day for current conditional will serves,
requested conditional will serves and the future requests for the next 5 years,
pushing the existing Sutter Creek Plant beyond even their permitted capacity.
“We have used about 10,000 gallons per day (extra) a year since I have
been here. If that holds steady, we have another 7 years of growth ahead,
however there are more projects applied for than that amount suggests,” states
Duke. Expanding the Sutter Creek Treatment Plant has become the most attractive
alternative to short term improvements at this time. Some other short term
improvements were then identified including processing and filter changes.
The
most promising was adding a
packaged plant, or a used plant, to the system. This could add anywhere from
20,000 to 100,000 gpd. The temporary facility would be built parallel to
the existing Sutter Creek Treatment Plant and the wastewater flows would be
divided between the two plants. Duke said that and packaged plant can be put
into operation within 6-8 months and remain operational for as many as 20
years, however the hope is that within a few years a new regional sewer plant will
be operational. In the meantime a funding mechanism must be developed for any
interim capacities available. The Interim Capacity Funding discussed will be paid for by new
development with the application of a surcharge to each connection fee, which will range between
$1,500 to $2,500. Also, interim capacity can be phased in to meet the
need, so any monies collected for interim phases can be paid back to the
developers if the phase is never implemented. The next steps towards moving to
an interim solution were then discussed.
The Sutter Creek Plant treatment
plant’s capacity will have to be re-evaluated based upon additional data. An
estimation of capacity needs on a year to year basis, instead of a 5 year basis.
Then a more detailed cost estimate of the interim treatment alternatives can be
developed, as well as investigating the option of purchasing a “used” treatment
plant.
Finally authorization must be obtained from governing boards in the area
to move forward with the design of the interim improvement. Duke added to the
list that he would like to start dialogue with developers to identify what
growth is reasonable on a year to year basis and then start planning various
upgrades based upon information gathered. “Some of the options to get a few thousand gallons are
actually fairly cheap. But we do not
want to create an incentive for everybody to hurry up and get in first to get
the cheap upgrades. We don’t want to get into a feeding frenzy,” said
Duke and many of the developers present at the meeting agreed.
A meeting to
discuss a long term solution is going to be held March 5th at 1:30pm
at the BOS chambers. However, in the meantime information that has been
developed as well as future meeting dates can be found online at the County’s
website by visiting www.co.amador.ca.us and clicking on the Regional Waste
Water Planning information link on the front page.
|